RDL-2000 Installation Guidelines
70-00144-01-01 Proprietary Redline Communications © 2011 Page 34 of 52 March 9, 2011
The following recommendations are general industry practices:
- The antenna mast/tower must be connected to the master earth ground.
- It is recommended to pre-assemble and test the RDL-2000 equipment (RDL-
2000, mounting bracket, and antenna) and connection wiring before final
installation of the units. Mount the pre-assembled RDL-2000 on the antenna
mast.
- Direct grounding from the RDL-2000, the mounting bracket, the antenna, and
the Ethernet cable surge protection to the same ground bus on the building
should be provided. Terminate ground wires using the grounding screws
provided on the RDL-2000 and the antenna mounting bracket.
- A lightning arrestor should be installed in series with the Ethernet cable as
close to the RDL-2000 unit as practical. The grounding wire should be
connected to the same termination point used for the tower or mast.
- A lightning arrestor should be installed in series with the Ethernet cable at the
point of entry to the building. The grounding wire should be connected to the
same termination point used for the tower or mast.
- . If AC PoE is used, the AC wall outlet ground for the indoor POE adapter
should be connected to the building grounding system.
Figure 22: Mounting - Air Terminal for Tower and Pole Deployments